Composting plant, airborne emissions management

Having built several composting plants previously, GCS recently supported a composting facility that had experienced corrosion in their duct system and required additional biofilter area due to changes in the usage of buildings within the facility.

GCS Supported:

- Appraisal of existing equipment through inspection and measurement of achieved flow and pressure.
- Assessment of extraction flow requirements
- Identification of optimal revised ductwork design to achieve the required extraction flow while maximising the utilisation of the remaining ductwork in serviceable condition
- Design of a new biofilter to meet the site’s airflow and space requirements utilising plastic crate system for cost and speed of deployment
- Specification of blower system, design of ductwork and valve system for blowers, blower tender process